Temporary Removal of Stolpersteine Due to Works on Plantage Middenlaan

5 October 2026

From Thursday, 1 October 2026, until 1 May 2027, Plantage Middenlaan, between Plantage Kerklaan and Plantage Parklaan, will undergo phased reconstruction works.

As part of these works, the Stolpersteine will be temporarily removed and carefully stored by the Municipality of Amsterdam’s regular street maintenance team.

The works will be carried out in phases:

  • From 1 October 2026: the Stolpersteine on the side of the Hollandsche Schouwburg will be removed and stored.
  • From 1 February 2027: the Stolpersteine on the side of the Holocaust Museum will be removed and stored.

Once the works have been completed, the Stolpersteine will be returned to their original locations.